HAN THAI VIETNAM METAL MACHINERY & COMPONENT MANUFACTURING PLANT
Project Overview
• Project Name: Manufacturing & Processing Plant for Machinery, Equipment, and Metal Components – Han Thai
• Investor: Han Thai Vietnam One Member Co., Ltd.
• Location: Lot 40, Street 11, Tan Duc Industrial Park, Huu Thanh Commune, Duc Hoa District, Long An Province, Vietnam
• Commencement Date: May 7, 2021
• Completion Date: January 11, 2022
Project Details
• Construction Duration: 6 months
• Total Land Area: 17,756 m²
• Total Construction Area: 6,738 m² (~38%)
• Total Floor Area: 7,893 m²
Main Components
|
Structure
|
Floors
|
Construction Area (m²)
|
Floor Area (m²)
|
|
3-Story Office Building
|
3
|
494
|
1,350
|
|
Workshop A
|
1
|
3,325
|
3,537.2
|
|
Workshop C
|
1
|
2,280
|
2,366.7
|
Key Highlights
· Efficient 6 months construction timeline
· Strategically located in Tan Duc Industrial Park, Long An
· Modern office and factory facilities supporting high-precision manufacturing
This project showcases our expertise in delivering high-quality industrial construction within tight deadlines. The Han Thai plant is now fully operational, contributing to Vietnam’s growing manufacturing sector.